Design Structures, LLC Weekly Report Project: Location: Week of: Report Date: Hood River Alliance Church Hood River, Oregon November 19, 2007 and November 26, 2007 – Weeks 4 & 5 November 30, 2007 WEEKLY PROGRESS: a. Completed light demo of the lights, wall panels, and window casing in the Fellowship hall north of the temporary fire wall. b. Completed hammering out hard rock during the building foundation excavation. c. Completed excavation for the building footings. d. Began excavation for the Storm Tech system. e. Hammered out hard rock during excavation of the Storm Tech system. f. Installed the temporary egress door required by the City of Hood River in the Fellowship Hall. g. Completed building foundation footing formwork. h. Poured the building foundation footing concrete. i. Removed the concrete footing formwork. j. Installed temporary power for the jobsite trailer. k. Received delivery of the 22’ Timberstrand studs. SCHEDULE STATUS: a. Begin framing exterior walls in the parking lot. b. Complete installation of the Storm Tech system. c. Receive delivery of additional framing material. d. Begin formwork for the concrete stem walls. e. Install the fire riser. f. Install a new sanitary sewer line. ISSUES AND CHALLENGES: a. Safety of the onlookers has improved since the beginning of the project. The congregation has been good about keeping there distance and working with all of the workers on site to have a safe project. ISSUES RELATED TO COSTS: a. There will be additional costs because we ran into hard rock while excavating for the Storm Tech system. PHOTOS (see attached):